PROJECT
STEPS |
|
|
|
CLIENT
ITEMS |
|
SIGN
CONTRACT -- $ = DOWNPAYMENT
Obtain building permit
Order windows and doors
Temporary covers and barriers
Sitework (tree removal) and make-up slab
Concrete Inspections
Pour concrete
|
|
At
least
3
weeks |
|
Move
furniture/personal items
Provide key for access
Provide utilities
Verify windows & exterior doors
Select tub & tub shower valves
Select recessed lighting
Select pre-fab fireplace |
|
|
|
|
|
|
|
Start
frame carpentry -- $ = SECOND payment
Demolition at House
Install structural ironwork
Install prefabricated fireplace
Install windows, exterior doors, exterior columns |
|
7 |
|
Select other plumbing fixtures
Select other light fixtures
Select roofing color
|
|
Start
roofing -- $ = THIRD payment
Rough-in plumbing
Rough-in HVAC
Rough-in electrical
Coordinate alarm system installation |
|
Weeks |
|
Select brick material
Select appliances
Provide alarm system wiring
|
|
Rough-in
Inspections -- $ = FOURTH payment
Insulation
Sheetrock
Install wood flooring |
|
. |
|
Select
garage door/opener
Select door/bath hardware
Select countertops
Review trim/cabinet details |
|
Start
interior trim -- $ = FIFTH payment
Install garage door & opener
Painting
Brickwork |
|
7 |
|
Select tile material
Select paint colors
Select carpeting & other flooring
|
|
Start
countertop installation -- $ = SIXTH payment
Install tile flooring and shower tile
Install plumbing fixtures, lighting, HVAC grilles
Install mirrors, shower doors, other glazing
Install hardware, bath accessories
Install gutters & downspouts
Finish wood flooring
Install carpeting, vinyl flooring
FINAL INSPECTIONS |
|
Weeks |
|
Review gutters locations
Select mirrors/shower doors
Approve wood floor stain color
Provide wallpaper & hanging
|
|
Handle "ITEMS TO COMPLETE" List
FINAL CLEAN-UP
$ = FINAL payment (Substantial Completion)
|
|
1
Week |
|
Create "Items to Complete" List
Provide landscaping
|
|
Handle "30 DAY" List : items discovered after
move-in
|
|
after
occupy |
|
Create "30 DAY" List
|